Schull Harbour pontoon installation in West Cork begins

The long-awaited pontoon at the popular boating harbour in Schull, West Cork looks to be finally underway with the arrival, this week, of a jack-up rig for pile driving.

As Afloat.ie reported in April, the Department of the Marine gave €112,500 for the installation of the pontoon which the local community has already procured at Schull in West Cork.

According to Schull Harbour Sailing Club, the contract for the North Harbour pontoon was expected to take six weeks to complete, but due to favourable weather the contractor L&M Keating are expecting to have it completed for Calves Week in early August.

Other West Cork locations also got funding for improvements – €56,250 for Glengarriff Pier to upgrade and improve the existing pier, including new steel steps and safety rails.

Work has also recently been completed to new boating facilities at Cape Clear Island, as Afloat.ie reported here.

As our picture above shows the new Schull facility will be a welcome addition in the popular harbour for both commercial and leisure craft. It’s another valuable asset for boaters exploring the sailing wonders of West Cork.

This story is from afloat.ie